Tobyhanna Building Renovations

Procurement
USACE Charleston District
Project Type
Complete Renovation
Location
Tobyhanna Army Depot, PA
Total Cost
$17,664,437.76
The interior and exterior renovation work included:
Replacement of the stucco and EIFS finished with EIFS
Demolition and reconstruction/enclosure of the loading dock at Bay 2, including HVAC, fire protection, power, and lighting
Removal of the ABA entrance barrier by providing a pedestrian ramp
Addition of a new roof at the Administrative area and Docks 2 and 4
Replacement of the lighting in the warehouse areas
Renovation of the Bay 3 Administrative area, including new HVAC, electrical, interior finishes, and reconfiguration of interior walls
Replacement of the fire suppression system to accommodate Group A Plastics, including a new fire pump room at loading dock 2 for increased water supply requirements
Installation of a new Public Address (PAVIS) system.